Analysis of Project Owner Satisfaction on the Performance of Supervisory Consultants on Road Construction Projects at Road and Bridge Maintenance Section of the Banjarbaru City Public Works Service, South Kalimantan

Main Article Content

Rusna Apriani
Irfan Prasetia

Abstract

During the outbreak of Covid-19 disease, the Banjarbaru City Government allocates most of the APBD funds for handling Covid-19 (Refocusing) including funds for the implementation of road infrastructure from 2020 until 2021. For efficiency, the step taken is to combine several streets on different packages to become one with the same supervisory consultant package. Based on data, supervisory consultants are mostly domiciled outside Banjarbaru City. In addition viewed of the project location which supervised, location packages of construction work are quite far away from each other. In this Covid-19 pandemic condition, Banjarbaru city participated in implementing restrictions on community activities (PPKM) by blocking several city entry points. With these restrictions, communication between supervisory consultants and project owners during the implementation of work is less effective because mostly implemented online so that it can affect the performance of most supervisory consultants. Therefore, an analysis of job owner satisfaction with the performance of supervisory consultants on road construction in Banjarbaru City needs to be done, especially in this Covid-19 era.


The study was conducted by collecting primary data obtained through questionnaires on a sample of sources at Dinas Pekerjaan Umum Kota Banjarbaru (Cipta Karya & Bina Marga). Data were analyzed using the computer program SPSS version 26.00 (Statistical Product and Service Solution). To determine the level of participant satisfaction, the Customer Satisfaction Index (CSI) method is used. Meanwhile, to determine the service factors that need to be improved, the Importance Performance Analysis (IPA) method is used. The results of the respondents' answers in the questionnaire will be analyzed by using Importance Performance Analysis (IPA). Variables that located in zone A or the main priority will be the focus of determining the performance improvement strategy of supervisory consultants.


Based on an analysis of 3(three) indicators with the following levels of satisfaction: Administrative Indicators of 68.84% (Satisfied), Monitoring Indicators of 74.81% (Satisfied), and Ability Indicators of 73.78% (Satisfied). Based on the analysis results, the dominant factors in improving performance, including in quadrant A, are the reporting of work progress activities and reporting of the results of the supervisory consultant activities, the supervision factor for the work method of construction during Covid-19, the ability factor to be present in the midst of the government's policy of enforcing the Enforcement of Restrictions on Community Activities (PPKM) and the factor of communication and coordination ability with the project owner by minimizing direct contact (Virtual).


IMG8377.jpg


Article Details

How to Cite
Apriani, R., & Prasetia, I. (2023). Analysis of Project Owner Satisfaction on the Performance of Supervisory Consultants on Road Construction Projects at Road and Bridge Maintenance Section of the Banjarbaru City Public Works Service, South Kalimantan. Technium: Romanian Journal of Applied Sciences and Technology, 5, 60–73. https://doi.org/10.47577/technium.v5i.8377
Section
Articles

References

Azwar, Saifudin. 1986. Validity and Reliability. Jakarta: Rineka Cipta

Ansari. 2009. Communication of Mathematical Concepts and Applications. Banda Aceh: Yayasan Pena

Cushway. 2002. Performance in social organization. Jakarta: Rineka Cipta

Cooper, D. R., & Schindler, P. S.. 2006. Business Research Methods.

Dimyati, Handan dan Nurjaman Kadar. 2014. Project Management. CV Pustaka Setia

Engel, J.F..Blackwell, R.D. and Miniard, P.W. 1995. Consumer Behavior, 8th d, Orlando: The Dryden Press

Ervianto, Wulfram I. 2002. Construction Project Management, Yogyakarta: Andi

Ervianto, Wulfram I. 2005. Construction Project Management, Edisi 2. Yogyakarta: Andi

Ervianto, Wulfram I. 2009. Construction Project Management, Jakarta: Graha Ilmu

Ervianto, Wulfram I. 2011. Construction Project Management. Yogyakarta: Andi

Gibson & Ivancevich, Donnelly. 1997. Organizational Construction Project Management, Structural Behavior, Translation Process Agus Dharma. Jakarta: Erlangga

Ghozali, I. 2009. Econometrics Theory, Concepts and Applications with SPSS 17. Semarang: Badan Penerbit Universitas Diponegoro

Harsian. 2020. Owner satisfaction with the Performance of the Supervising Consultant on Construction Projects at the Public Works and Spatial Planning Office of West Sumatra Province.

Noor, Ahsan. 2020. Analysis of Satisfaction of BBPJN XI Banjarmasin on the Performance of Supervisory Consultants in Bridge Construction Project Work in South Kalimantan. Universitas Lambung Mangkurat. Kalimantan Selatan

Oglesby, Clarkson & Hicks, R. 1990. Road Engineering. Jakarta

Peraturan Menteri Pekerjaan Umum No: 08/PRT/M/2011 08/PRT/M/2011 tentang Pembagian Subklasifikasi dan Subkualifikasi Usaha Jasa Konstruksi. Kementrian Pekerjaan Umum Republik Indonesia

Presiden Republik Indonesia Nomor 70 tahun 2012 Tentang Perubahan Kedua Atas Peraturan Presiden Nomor 54 Tahun 2010 Tentang Pengadaan Barang/Jasa Pemerintah

Rangkuti, 2005. SWOT Analysis. Case Dissecting Techniques. Jakarta: Gramedia Pustaka Utama

Shenson. 1990. Successful Event Management. London: Thomson

Soeharto, Iman. 1995. Project Management: From Conceptual to Operational. Jakarta: Erlangga

Soeharto, Iman. 2001. Project Management. Jakarta: Erlangga

Soelasih,Y. 2004. Analysis of Consumer Satisfaction on Service Quality of Hotel X in Jakarta 4(2)

Suryabrata. 2004. Research methodology. Yogyakarta: Pustaka Pelajar

Simanjuntak. 2005. Management and Evaluation of Performance. Lembaga Penerbit Fakultas Ekonomi UI. Jakarta

Shehila Riany. 2020. Performance Analysis of Supervisory Consultants in the Field of Water Resources Public works and Spatial Planning of Tapin District.

Tarore, H. & Mandagi, R. J. M. 2006. Project and Construction Management System. Pasca Sarjana Universitas Sam Ratulangi, Manado

Tjiptono. 2011. Capital Markets in Indonesia, 3rd Edition. Jakarta: Salemba Empat

Taunay, E. G. P., 2013. Analysis of Consumer Satisfaction on the Quality of Health Services. Scientific Journals Media Engineering Vol. 5. No1, Oktober 2013

Tomigulung, Fergita. 2013. Supervision Consultant Performance on Road and Bridge Projects in North Sulawesi. Universitas Sam Ratulangi. Sulawesi Utara

Visnu Aria Wardhana and Trihono Kadri. 2014. in general the role of a consultant in SiNMag 6, 2020 ISSN 2656-5919 Vol.4, No.1 Prosiding Heflima S. Harsian 1), Zaitul 2) Simposium Nasional Magister Page 485

Walizer, Sadiman, & Wienir. 1987. Research Methods and Analysis: Searching for Relationships. Jakarta: Erlangga